Stormwater Management and Road Tunnel (SMART), Malaysia
 
Internationally recognised as highly innovative, Stormwater Management and Road Tunnel (SMART) is a first of its kind in the world, incorporating a stormwater tunnel and a motorway. Acclaimed as an iconic project for its outstanding concept, affordability and functionality, SMART is an example of world-class infrastructure Gamuda is capable of.
 

Feature highlights:

  • A 7km stormwater tunnel to contain and divert flood water out and into a storage reservoir.
  • A 3km motorway integrated with the stormwater tunnel to provide an alternate route for motorists entering and exiting the southern gateway of Kuala Lumpur.

Three-mode operation: The SMART system works on the three-mode principle of operation based on flood discharge and operation status of the motorway.

Click on box to view information.

 

Tunnel safety: SMART has additional safety features that are unique over and above the features seen in a normal motorway tunnel.

Safety Features

   
 

Gamuda sold the concept of SMART to the Malaysian Government on the strength that it was an innovative yet practical and affordable solution to mitigate flooding and traffic congestion problems in central Kuala Lumpur.

Studies undertaken showed concentration at the confluence of major rivers during heavy rainfall, causing recurring flooding in the city. SMART was designed to divert flood water from entering this critical location of the confluence via a holding basin, storage reservoir and a bypass tunnel.

Client
Government of Malaysia
Concessionaire
Syarikat Mengurus Air Banjir & Terowong Sdn Bhd
Turnkey Contractor MMC Berhad – Gamuda Berhad Joint Venture

Scope of Works

  • Design
  • Supervision
  • Construction
  • Commissioning
Construction Cost
US$510 million
Stormwater Tunnel
Length:
9.7km
Diameter:
13.2m (outer diameter)
Tunnelling Method:
Tunnel Boring Machine (TBM)
TBM Type:

Slurry Shield
Largest in South East Asia & 2nd Largest in Asia

Motorway Tunnel
Length:
3km
Structure type:
Double Deck

Ingress and Egress:

Connections’ Length:

1.5km at Jalan Sultan Ismail

1.4km at Jalan Tun Razak

1.6km at KL-Seremban Highway

Links:

City Centre near Kg. Pandan Roundabout

KL-Seremban Highway near RMAF


Other Features of SMART
Safety System in the Motorway Tunnel:
  • Automated water-tight twin flood control gates at both ends of the motorway
  • Cross Passage between decks at 250m intervals
  • Ventilation/escape shafts at 1km intervals
  • Equipped with fire fighting equipment, telecommunication and surveillance system at 1km intervals along the motorway tunnel
Components
  • 9.7km stormwater by-pass tunnel
  • 3km double-deck motorway within stormwater tunnel
  • Ingress and egress connections to the motorway tunnel linking the southern gateway to the city centre
  • Holding basin complete with diversion and tunnel intake structures
  • Storage reservoir and a twin-box culvert to release flood discharge
  • State-of-the-art operations control room equipped with the latest systems in operations management, surveillance and maintenance of the SMART system

 

 