Sungai Selangor Dam, Sungai Selangor Water Supply Scheme Phase 3 (SSP3), Malaysia
 

Environmental protection was a major factor and this was implemented with efficient planning and management to ensure minimum impact on the environment during and post construction period.

The building of the Sungai Selangor Dam provided a critical solution to meeting water requirements of industrial and population growth in Selangor and Kuala Lumpur.

 


As part of several components constituting Sungai Selangor Water Supply Scheme Phase 3, the dam was designed as a regulating dam and was built to hold a


storage capacity of 235 million cubic metres of water. It is rockfill 110m high and situated at the founded on a solid granite bedrock just downstream of the confluence of Sungai Selangor and Sungai Gerachi.

The dam embankment comprises an impervious earth core covered with an external rockfill. In between, there is a layer filter material consisting of 0.62 million cubic metres of granular material. The dam, 400m wide at the base, 800m long and 110m high, is built up of 1.2 million cubic metres of clay core and 6.4 million cubic metres of granite. At full supply, the inundated areas is just 600 ha, making it the dam with the largest storage capacity relative to the area inundated.

Completed ahead of schedule, dam impoundment commenced on April 25, 2003 and reached its full supply level which is 220, (above sea level) on April 13, 2004.

Client
The Selangor State Government of Malaysia
Concessionaire Syarikat Pengeluar Air Sungai Selangor Sdn Bhd
EPC Contractor Gamuda-KDEB-TSWA Joint Venture

Scope of Works

  • Design
  • Supervision
  • Construction
  • Commissioning
Project Facts

Components of SSP3

Regulating dam over Sungai Selangor that entails:

  • realignment of a 7.7km section of Federal Route 55 (Kuala Kubu Bharu-GAP Road)
  • resettlement of 2 villages and the Institute Kemahiran Belia Negara (IKBN)

Water treatment plants

  • 250 MLD (125MLD x 2) intake and treatment works at Rasa to serve Northern Selangor
  • 800MLD (400MLD x 2) intake and treatment works at Bukit Badong to serve the Federal Territory Dam

  • Storage: 235 million cubic metres
  • Location: 5km east of Kuala Kubu Bharu, at KM66.5 of Kuala Kubu Bharu-Bukit Fraser Road
  • Height: 110m
  • Type: Rock filled, with clay core
  • Crest length: 800m
  • Catchment Area: 197sq km, mainly secondary jungle
  • Impoundment: 600 hectares/6sq km (3% of catchment area)

 

 